电缆警示桩施工时的安装方法以及质量要求

来源:http://www.binzhouhengtong.com/ 发布时间:日期:2022-06-25 0
警示桩也叫警示桩、标志桩等顾名思义是起到指示、提醒的作用的,一般用在公路交通、电力电缆、石油燃气等,由于使用广泛,作用重要,因此正确的警示桩(标志桩)的设置是非常有必要的。下面我们来看看电缆警示桩施工时的安装方法以及质量要求内容吧。
Warning piles are also called safety warning piles, sign piles, etc. as the name suggests, they play the role of indication and reminder. They are generally used in highway traffic, power cables, oil and gas, etc. because they are widely used and play an important role, it is very necessary to set correct warning piles (sign piles). Now let's take a look at the installation method and quality requirements of cable warning pile construction.
警示桩的质量要求
Quality requirements for warning piles
1、质量要求按图纸设计和施工技术规范及业主要求进行。
1. The quality requirements shall be in accordance with the drawing design and construction technical specifications and the owner's requirements.
2、道口标桩、警示桩应保证标桩垂直无歪斜,并保证位置正确,颜色鲜明、醒目。
2. The crossing stake and warning stake shall ensure that the stake is vertical without skew, and the position is correct, and the color is bright and eye-catching.
3、道口标桩在公路沿线较小交叉路口的两侧对称设置,每侧一根,用来提醒主线车辆提高警惕。
3. The crossing stake is symmetrically set on both sides of the smaller intersections along the highway, one on each side to remind the mainline vehicles to be vigilant.
4、埋设深度、间距、高出地面尺寸严格按设计图纸施工。
4. The buried depth, spacing and height above the ground shall be constructed in strict accordance with the design drawings.
警示桩施工方法
Construction method of warning pile
1、工艺流程。施工区域交通管制→施工放样→基础施工(钻机钻孔)→警示桩加工制作→现场安装(灌浆、安管)→现场清理、撤离。
1. Process flow. Traffic control in the construction area → construction setting out → foundation construction (drilling rig) → warning pile processing and fabrication → site installation (grouting and pipe installation) → site cleaning and evacuation.
电缆警示桩
2、施工放样。警示桩为新增工程量,安装位置由业主、监理单位现场确定。
2. Construction setting out. Warning piles are new quantities, and the installation position shall be determined by the owner and the supervisor on site.
3、警示桩基础。警示桩基础孔洞为钻机钻孔,孔深30cm,直径150mm(根据警示桩的采购规格设计)。按照图纸规范钻孔,并将桩底正平压实。
3. Warning pile foundation. The warning pile foundation hole is drilled by a drill, with a hole depth of 30cm and a diameter of 150mm (designed according to the purchase specification of the warning pile). Drill holes according to the drawings and specifications, and compact the pile bottom.
警示桩安装
Installation of warning pile
(1)警示桩安装应保证桩柱垂直无歪斜,并保证位置正确,颜色鲜明、醒目。
(1) The installation of warning piles shall ensure that the piles are vertical without deflection, and that the positions are correct and the colors are bright and eye-catching.
(2)警示桩安装完毕后应进行路面清扫,在清扫过程中,不应损坏桩身反光膜或产生其他缺陷。
(2) After the installation of warning piles, the road surface shall be cleaned. During the cleaning process, the pile reflective film shall not be damaged or other defects shall not occur.
(3)电缆警示桩桩内采用M10砂浆灌浆,地下部分深度为30cm。
(3) M10 mortar is used for grouting in the pile, and the depth of the underground part is 30cm.
以上就是问题解答的相关内容了,希望能够帮助到大家,如对这一问题还存在任何疑问,都欢迎关注我们网站http://www.binzhouhengtong.com并咨询我们的工作人员,将竭诚为您服务。
The above is the relevant content of the question answer. I hope it can help you. If you still have any questions about this problem, you are welcome to follow our website http://www.binzhouhengtong.com And consult our staff, will serve you wholeheartedly.